For updates regarding the Bridge Working happening for the next few months please refer to this page.   The State will be providing bi-weekly updates that we will post here.  

2023 Bridge Work Schedule   (updated 4/18/23)

Weekly Construction Update for the week ending 7/8/2023.

Last week, the Contractor continued installing deck formwork on southside of bridge.

This week, the Contractor installed welded shear connectors and continued deck formwork installation.

  • Traffic impacts next week:
    • Single lane closure with temporary traffic signals.
For those unfamiliar with the project, the concrete bridge deck will be replaced and widened, to allow for a new, wider sidewalk on the north side of the bridge, new pedestrian and bicycle-friendly traffic barriers, and a new waterline will be installed underneath the bridge between the girders. If you have any concerns or comments, please do not hesitate to contact Dan Doumit (Project Team Lead, 360-430-8869 or Nathan Retherford (Lead Inspector, 360-560-1867)